Grounds Superintendent Project List
Revised Project List - 5-15 Year Plan. As of 2008
| Item |
Description |
Total Item Cost |
Priority |
Cost/Yr for all projects |
| Drainage |
Finish off of drainage as required. The "Exit"
drainage for our existing system must be improved immediately.
Proposed timing 2008- 2010 |
$75,000.00 |
1 |
$25,000.00 |
| New Water Source |
We must locate an alternate water source. The "raw
water" we are now getting from the Husky Upgrader line is uncertain
at best. Proposed Timing 2009-2010 |
? |
1a |
? |
| Tee Box Renovations |
We have a proposal for the tee box renovations in
place, we just need to adjust the costs and numbers accordingly when
we start the work. Proposed Timing 2009-2012 |
$350,000.00 |
2 |
$175,000.00 |
| Bunkers |
Repairs as required to bunkers will be taken care
of through maintenance. Other work such as proper drainage require’s
capital funding. Proposed Timing 2010-2012 |
$75,000.00 |
3 |
$25,000.00 |
| Ponds |
All ponds require major rework. This includes,
cleaning, deepening, and rip rapping or placing ties along banks to
maintain banks. #17 pond is first in line for renovation to help
with the drainage on #10 approach and bush. Proposed Timing
2012-2017 |
$750,000.00 |
4 |
$125,000.00 |
| # 17 Fairway |
Left side of hole from trees to green requires
major repair and drainage. We will then be able to pump 17 fairway
holding catch basin either to pond or to the drainage piping.
Proposed Timing 2012 |
$150,000.00 |
5 |
$150,000.00 |
| Cart Path Paving |
Budget a % each year. We should budget $ 25,000/ yr
and every three years do $ 75,000 worth of work. This would take us
roughly 15 years to complete. Proposed Timing 2008-2023 first part
of paving $ 75,000-2011, 2nd- 2014, 3rd 2017, 4th- 2020, 5th- 2023 |
$375,000.00 |
6 |
$25,000.00 |
| # 5 Fairway |
Drain from right side of fairway over to pond on
left. Clean up left side of fairway at same time by making a small
waste bunker down left side to end of first pond Proposed Timing
2018 |
$75,000.00 |
7 |
$75,000.00 |
| Project Totals |
|
|
$1,850,000.00 |
|
|
|
 |